|
3.1.1 Contracting authorities
Defence procurement covers a very wide spectrum ranging from research and
development through to the production of equipment and spare parts, the
preparation of documentation, training, consultancy services and maintenance.
The nature and extent of a particular procurement determines which branch of the
defence establishment will be responsible for managing the project. Major system
and equipment contracts are concluded and managed by the Materiel Commands of
the Service concerned or by the Norwegian Defence Communications and Data
Services Administration. If the forecast project cost exceeds NOK 50 million,
Headquarters Defence Command Norway seeks Ministry of Defence approval both at
the tender stage and for the placing of the contract. The Norwegian Defence
Construction Service is responsible for contracts relating to building and
construction work. Procurement contracts are also placed at levels of the
defence organisation. Headquarters Defence Command Norway, Defence Commands
North Norway and South Norway, the various District Commands, indeed even
individual local units, are all involved to a greater or lesser degree in
procurement activities.
3.1.2 Procurement plans
The Parliament decides the objectives for the future development of the
Armed Forces. These are set out in the long-term parliamentary reports which lay
down guidelines for the activities and plans of the Armed Forces. A full listing
of current defence projects, including those approved but not yet initiated, is
contained in the Defence Materiel Plan. This is published annually and is
usually revised twice. The Chief of Defence's so-called «Document No. 2»
(DOK 2) is issued annually and covers defence investment planned for the next 5
years. These documents are based on approved force levels and objectives and
result from political, economic, technical and tactical considerations. The
plans list the weapon systems and other equipment that the Armed Forces are
planning to acquire over the next few years. A good deal of the content of these
documents is normally classified but each year the Ministry of Defence also
produces an unclassified supplement in connection with the submission of the
defence budget to the Parliament. This outlines the planned investment for the
coming year in terms of the different systems, equipment and construction
projects involved.
There is no overall and detailed set of plans covering procurement of the
goods and services required to support the operation of the Armed Forces from
year to year. These purchases are made at all levels in the defence organisation
throughout the country. A large proportion of the total is spent on procurements
from local industry in the districts where units and establishments are located.
3.1.3 System responsibility
For the procurement of major systems the Materiel Command concerned will
usually place a contract with a single company which will then act as the main
contractor and be responsible for overall fulfilment of all aspects of the
contract. The main contractor's competence in terms of technical expertise,
administrative ability, financial standing etc is thus of prime importance.
The procurement of large and complex systems takes a long time and is very
demanding in terms of resources, both human and financial. To relieve the
already overburdened defence procurement organisation, the systems supplier must
be able to manage his own subcontractors and the contractor must therefore be
financed accordingly in order to limit, as far as possible, any risk to the
Armed Forces. Selection of subcontractors for major tasks will often need to be
approved by the contracting authority.
3.1.4 Norwegian subcontractors
In the case of procurement from foreign suppliers, every effort is made to
motivate the supplier to use Norwegian subcontractors. This may be done by the
contracting authority reserving the right to approve individual subcontractors
or by placing contracts for subsystems or components separately for inclusion in
the final product. Efforts are also made to arrange production under licence by
Norwegian companies. Success here will depend largely on the capability and
level of expertise of the companies concerned.

|